Construction Alerts
Town Center Four Tenant Fit-out
Construction is underway at Town Center Four, and work is expected to affect on-site amenity spaces. This expansion supports UVA Health's growth in lab services. Read about the UVA Health expansion here.
North Fork Meeting Center Temporary Relocation
The North Fork Meeting Center has temporarily relocated to Town Center Three. To reserve the space or check availability, contact Michele at maichs@uvafoundation.com.
Navbar Temporary Relocation
Beginning in late November, enjoy Navbar's coffee, smoothies, and snacks at the Foods of All Nations Café in Town Center Three.
- Navbar will close on or around November 19 and reopen in the café on November 23, 2026
Success Studio North
Success Studio North remains open during construction. We will communicate any operational changes to studio members in advance.
Construction Updates:
Week of 11/16-11/20:
- Medium to loud noise levels due to wall framing and overhead MEP work on Floor 2
- Medium to low noise levels due to spray fireproofing operations on Floor 2 and Floor 1
- Odors may be present due to spray fireproofing operations on Floor 2 and Floor 1
Week of 11/23-11/27 (no work on 11/26 & 11/27):
- Medium to loud noise levels due to wall framing and overhead MEP work on Floor 2
- Medium to low noise levels due to spray fireproofing operations on Floor 1
- Odors may be present due to spray fireproofing operations on Floor 1
Week of 11/30-12/4:
- Medium to loud noise levels due to wall framing and overhead MEP work on Floor 2
- Medium to low noise levels due to spray fireproofing operations on Floor 1
- Odors may be present due to spray fireproofing operations on Floor 1